Project

Wire Rod Mill Revamping

  • Mechanical and piping installation
Service
Mechanical Dismantling, Mechanical, Piping and Steel Structures Installation
Location
Italy
Year
2022
Technological supplier
SMS Group Spa

Ferretti Construction carried out the mechanical dismantling and installation, along with the installation of piping and steel structures, as part of the revamping of a wire rod mill and its associated stands.

The project, completed between August and October 2022, involved:

  • Dismantling of 200 tons of mechanical equipment
  • Installation of 145 tons of new mechanical systems
  • Installation of 13 tons of piping and supports
  • Assembly of 25 tons of steel structures

All activities were executed with a strong focus on precision alignment and assembly, ensuring seamless integration with the existing plant.

Site period: August – October 2022