Project

Rolling Mill Revamping

  • Fast-Track Revamping
Service
Civil Detail Design and Civil works on a fast-track revamping basis
Location
Sremska Mitrovica, Serbia
Year
2022
Shut-down period
10 calendar days (2 days ahead of schedule)
Technological supplier
Danieli Spa

Ferretti Construction carried out the revamping of the rolling mill foundations for the installation of a new billet welding machine at the Sremska Mitrovica plant in Serbia.
The intervention was executed during a 10-day calendar shut-down and successfully completed using fast-track revamping technology. Civil works were finished two days ahead of the initial schedule, allowing the entire project to be completed in just 10 days, compared to the 12 days specified in the contract.

Timeline:
On-site presence: November 2022 – January 2023
Operational shutdown: 10 calendar days (delivery 2 days ahead of schedule)