Project

Intermediate Mill Revamping

  • Fast-Track Revamping
Service
Civil Detail Design and Civil works on a fast-track revamping basis
Location
Italy
Year
August 2022 + December 2022
Shut-down period
12 calendar days (3 days ahead of schedule)
+ 14 calendar days (2 days ahead of schedule)
Technological supplier
Danieli Spa

Ferretti Construction carried out the civil detailed design and execution of civil works for the revamping of an intermediate rolling mill in Italy, using a Fast-Track Revamping approach to ensure speed and operational efficiency.

The project was executed during two scheduled shutdowns, both completed ahead of time:

  • Shutdown #1: planned for 12 days, completed 3 days early
  • Shutdown #2: planned for 14 days, completed 2 days early

The scope of work included approximately 5.500 m³ of excavation and demolition and the casting of over 4.500 m³ of structural reinforcement concrete, all performed with high operational efficiency and strict quality control.