Project
New Slitting Line Foundations
Service
Civil Detail Design and Civil WorksLocation
ItalyYear
2024Technological supplier
FIMI Group SpaFerretti Construction was responsible for the detailed design and execution of the civil works for the construction of new foundations for a slitting line at a production facility in Guastalla (RE), Italy.
The project required deep excavation down to -8,00 m, with a finished pit depth of -7,00 m, below the groundwater table located at -2,50 m. These conditions demanded high technical standards for water management and structural stability.
Construction period: